Skip to main content
Back to projects

Verinsko BESS

Verinsko, Sofia, BulgariaRenewable Energy

AnnouncedOperational
Overview

Verinsko is a co-located project featuring a 36.6 MWh battery, with Sunotec acting as the EPC. (Source: ESS News - https://www.ess-news.com/2025/10/16/sunotec-secures-financing-for-763-mwh-solar-and-storage-portfolio-in-bulgaria)

Project Timeline

No timeline events recorded yet.

Procurement
Expected procurement
Not publicly confirmed
Expected construction start
Not publicly confirmed
Expected commissioning
Not publicly confirmed
Expected completion
Not publicly confirmed
0 tender(s) linked to this project.
Tenders

No tenders linked yet.

Sources

No sources recorded yet.

Quick Facts
Country
Bulgaria
Region
Sofia
City
Verinsko
Industry
Renewable Energy
Commodity
Not publicly confirmed
Project type
Plant
Owner
Sunotec / Solaris Holding
Operator
Sunotec
CAPEX
Not publicly confirmed
Capacity
36.6 MWh
Current Status
Current stage
Operational
Status
Active
Fact classification
Announced Information
Verification
Unverified
Last verified
Not publicly confirmed
Source Transparency
Last updated
10/9/2026
Verified
Unverified
Fact classification
Announced Information
Sources
1 sources

Key Project Contacts

No verified contacts published yet. Have a public contact? .

Frequently Asked Questions

Verinsko BESS is currently at the Operational stage of its industrial lifecycle. This stage indicates where the project sits in its development journey, from early exploration and feasibility studies through to construction, commissioning, and operations. Understanding the current stage helps you identify what procurement packages are coming next, what contractors are being engaged, and when tender opportunities are likely to open. You can use the stage filter on the Projects page to find other projects at the same stage.

Report incorrect information

Spotted something wrong? Project Atlas verifies every record against its sources. Report corrections through the contact channel.