Nangbeto Hydropower Plant

Nangbeto Dam

Nangbeto, Plateaux, TogoRenewable Energy

AnnouncedOperational
Overview

An existing 65 MW hydroelectric dam on the Mono River, providing power to both Togo and Benin. (Source: TendersInfo - https://www.tendersinfo.com/togo-projects.php)

Project Timeline

No timeline events recorded yet.

Procurement
Expected procurement
Not publicly confirmed
Expected construction start
1984-01-01
Expected commissioning
1987-09-01
Expected completion
Not publicly confirmed
0 tender(s) linked to this project.
Tenders

No tenders linked yet.

Sources

No sources recorded yet.

Quick Facts
Country
Togo
Region
Plateaux
City
Nangbeto
Industry
Renewable Energy
Commodity
Not publicly confirmed
Project type
Plant
Owner
Communauté Electrique du Bénin (CEB)
Operator
CEB
CAPEX
140,000,000 USD
Capacity
65 MW
Current Status
Current stage
Operational
Status
Active
Fact classification
Announced Information
Verification
Unverified
Last verified
Not publicly confirmed
Source Transparency
Last updated
10/9/2026
Verified
Unverified
Fact classification
Announced Information
Sources
1 sources

Key Project Contacts

No verified contacts published yet. Have a public contact? .

Frequently Asked Questions

Nangbeto Hydropower Plant is currently at the Operational stage of its industrial lifecycle. This stage indicates where the project sits in its development journey, from early exploration and feasibility studies through to construction, commissioning, and operations. Understanding the current stage helps you identify what procurement packages are coming next, what contractors are being engaged, and when tender opportunities are likely to open. You can use the stage filter on the Projects page to find other projects at the same stage.